James Fisher successfully completed the world’s first abrasive cut on a 10m-diameter offshore wind turbine monopile, on behalf of an international energy operator.
Customer challenge
An offshore wind operator identified a flaw in the foundation of a 10m diameter monopile after installation. With no proven method to safely sever this large structure, they faced a significant challenge in safely removing it while minimising downtime and reducing environmental impact.
Solution for our customer
James Fisher designed, built, tested and deployed a bespoke external abrasive cutting tool – the first of its kind capable of tackling monopiles of this scale. The tool was deployed subsea to complete an abrasive waterjet cut in one pass.
Customer impact
-
Safe and rapid removal of the flawed monopile, enabling recovery to the vessel deck without incident
-
Reduced environmental impact thanks to shorter operational timeframe
-
Cost efficiency through a purpose-built tool which avoided the need for multiple interventions
-
This approach combined the efficiency and reliability developed through decades of oil and gas projects with innovation tailored to offshore wind’s unique demands

Download the "World-first 10m diameter wind turbine monopile severance" case study to share with your team.
More case studies
Read article
Skandi Singapore: 15 years of proven saturation diving capability
Read article
Safeguarding animal feed supply through Cattedown Wharves
Read article
Blade inspection, repair and life extension services for a leading UK energy operator
Read article
Supporting safe, large-scale ammonia bunkering at the Port of Rotterdam
Read article
JFD completes hyperbaric test for Verlume’s Orah subsea enclosure, supported by James Fisher Energy’s R2S technology
Read article
Ageing Assets: Helping South America’s Onshore Energy Industry Plan with Confidence
Read article
New Uruguay hub delivers faster, more resilient ship-to-ship support across South America
Read article