A leading renewable energy installation contractor required James Fisher’s powerful JetFlow 100 controlled flow excavation solution to trench an export cable in a busy harbour offshore New York City.
Customer challenge
Our customer required safe and rapid trenching for an 11in cable at the entrance to a crowded harbour, with minimal disruption to marine traffic, to support the burial of offshore wind farm export cables.
Key statistics
Solution for our customer
The JetFlow 100 controlled flow excavation system removed sand, clay and silt at average speeds of nearly 3m/min, beyond initial 1.5m/min projections. Excavation activity created the trench ahead of schedule with additional telemetry equipment fitted, reducing vessel days and additional survey costs.
Impact to our customer
- Nearly 3m/min average excavation speed, accelerating trenching without harbour downtime
- Fewer vessel days, reducing cost to customer
- Compact deck footprint, maximising vessel space
- Integrated sonar monitoring, supporting safe excavation in poor visibility
- Additional survey and telemetry equipment temporarily installed at customer’s request, enabling pre-and post-lay surveys to be completed efficiently with one tool
- Excavation completed in under 177 operational hours, reducing offshore time
- Proven CFE performance, supporting critical grid connection activity