JFD combined its hyperbaric testing expertise with James Fisher Energy’s R2S technology to support qualification of Verlume’sOrah subsea enclosure in Aberdeen, UK.

 

Challenge

Ahead of offshore deployment, Verlume needed to verify Orah’s performance under representative subsea conditions. The 10-tonne enclosure also required careful assessment of available space at JFD’s National Hyperbaric Centre (NHC).

 

Solution

JFD used James Fisher Energy’s R2S digital twin technology to create a trusted 360-degree view of the hyperbaric chamber, supporting spatial planning and enabling Verlumeto maximise Orah’s capacity. At its NHC, JFD conducted controlled pressure testing to verify the enclosure’s integrity and performance.

Key features

Largest vessel ever tested at JFD's NHC t

Customer impact

  • Verified performance, integrity and depth capability of largest vessel ever tested at JFD’s NHC
  • Used R2S digital twin technology to support spatial planning and capacity maximisation during Orah’s design phase
  • Further de-risked Orah ahead of planned offshore deployment
  • Demonstrated James Fisher’s combined digital and engineering capabilities to support complex subsea technology qualification
This programme demonstrates the scale and flexibility of JFD’s hyperbaric testing capability. By combining James Fisher Energy’s digital expertise with our specialist testing facilities, Verlume was able to verify Orah’s performance and progress towards offshore deployment.
Andrew Laing, Commercial Diving Director, JFD
James Fisher is a global supplier of trusted engineering services across the industries we serve, with an unrivalled ability to develop innovative solutions that meet the constantly developing needs of our customers operating in challenging environments.